Meeting Time: June 18, 2020 at 9:00am PDT
The online Comment window has expired

Agenda Item

28. SUBJECT: METRO RED LINE SCADA REPLACEMENT AUTHORIZE: A. The Chief Executive Officer to increase the Contract Modification Authority (CMA) specific to Contract No. OP39603035 with ARINC Control and Information Systems (ARINC) in the amount of $3,357,496 increasing the total authorized contract amount from $15,551,028 to $18,908,524. B. The Chief Executive Officer to execute contract modifications up to the Board-approved CMA in an amount not to exceed $18,908,524. C. The purchase of additional coverage on the existing $15,000,000 supplemental project insurance in excess of ARINC's limited liability in an amount not-to-exceed $700,000. This action increases the total coverage cost from $1,449,000 to $2,149,000; D. An extension to the period of performance of Contract OP39603035 to December 31, 2021 to allow for SCADA-related work on the CLAX/AMC Station to be completed under this Contract.