22. SUBJECT: SOUNDWALL PACKAGE 11 HIGHWAY PROJECT ACTION: CONTRACT MODIFICATION
AUTHORIZE the Chief Executive Officer to:
EXECUTE Modification No. 19 to Contract No. C39033C1101-2 Soundwall Package 11 Highway Project for work above and beyond the original scope of services. This additional work is within the LOP budget and increases the total contract price in the amount of $860,000, from $66,041,760 to $66,901,760.